Chitral hydel power is a hydroelectric power station which is located on the right bank of Lutkho river and 5 Km upstream of Chitral city. The flow of Lutkho river was diverted by a 3.72 Km long channel. The power station is equipped with 2 units of 200 kW and 2 units of 300 kW each to cumulatively generate 1 MW of electricity. The power generated from the power station is being provided to the Chitral city through an 11 kV transmission line. The project was commissioned in 1975.[1]
| Chitral Hydel Power Station | |
|---|---|
| Official name | Chitral Hydel Power | 
| Location | Chitral, Khyber Pakhtunkhwa, Pakistan | 
| Purpose | Power Generation | 
| Owner(s) | Water and Power Development Authority (WAPDA) | 
| Power Station | |
| Turbines | 2 x 200 kW 2 x 300 kW | 
| Installed capacity | 1 MW | 
| Annual generation | 4.13 GWh | 
See also
References
- ↑ "Chitral Hydel Power". wapda.gov.pk. Retrieved 2022-07-25.
    This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.